RECPDCL Transfers Rajasthan Power Project to Apraava Energy
| Aspect | Details |
|---|---|
| Entity Involved | REC Power Development and Consultancy Limited (RECPDCL), Apraava Energy Private Limited (AEPL) |
| Project | Rajasthan IV-A Power Transmission Project |
| Location | Rajasthan Renewable Energy Zone Phase IV (Jaisalmer and Barmer complexes) |
| Project Scope | - Construction of 765/400 kV, 4x1500 MVA pooling station |
| - Construction of 400/220 kV, 5x500 MVA pooling station | |
| - Laying of 184.56 kilometers of 400 kV transmission line | |
| Timeline | Completion within 2 years |
| Capacity Addition | Enhances region's power transmission capacity |
| Impact | Supports Rajasthan's renewable energy objectives |
| Significance | Contributes to achieving 500 GW of installed electricity capacity from non-fossil fuel sources by 2030 |
| Development Model | Build, Own, Operate, and Transfer (BOOT) |
| BOOT Model Description | Investor delegates building, operation, and maintenance to another company for a limited time |