| Key Aspect | Details |
|---|---|
| Project Name | Mumbai-Ahmedabad High-Speed Rail (MAHSR) |
| Technology | E10 Shinkansen (Alfa-X) bullet train (first outside Japan) |
| Expected Launch | Early 2030s |
| Trial Trains | E5 Series (Hayabusa) for testing (arriving early 2026) |
| Trial Purpose | Test performance under Indian conditions (dust, heat) |
| E10 Features | Speed up to 400 kmph, improved safety, energy efficiency, comfort |
| Commercial Start in Japan | Expected by 2030 |
| Project Cost | ₹1.1-lakh-crore |
| Corridor Length | 508 km (Gujarat: 352 km, Maharashtra: 156 km) |
| Progress Highlights | - 21-km tunnel (Ghansoli-Shilphata) completed |
| - 310 km viaduct constructed | |
| - 15 river bridges ready | |
| - 5/12 stations completed | |
| Future Plans | Additional bullet train routes under consideration |